Report for December 2015
- Report Date
- December 2015
Achievements this period
- Final interviews conducted
- Draft review paper competed & issued for review
- Feedback meeting held with Project Sponsor
Issues
- Project Sponsor has requested some additional interviews & analysis work which will require an additional 3 days funding & will impact the timeline. Until this funding is confirmed the project will be on AMBER status.
Next steps
- Confirm additional funding & revised timeline
- Complete additional interviews & analysis
- Issue revised draft review paper
Target date | Title |
---|---|
15-Jan-2016 | Final paper delivered |
29-Jan-2016 | Project closure |
- Approved budget
- 10.0 days
- Activity this month
- 2.0 days
- Activity this year
- 10.0 days
- Activity to date
- 10.0 days
- Estimate to complete current year
- 0.5 days
- Estimate to complete future years
- 0.0 days