Report for November 2015

Report Date
November 2015

Achievements this period

  • A series of interviews have taken place with key stakeholders from RIR. ERI and EDINA

Issues

  • Issues securing confirmed interview dates due to previous diary commitments.  This will impact the delivery & closure milestones by about 2 weeks which pushes them into the University shutdown period.

Next steps

  • Final interviews to be conducted
  • Draft technical report and analysis summary papers to be produced & shared with Project Sponsor

 

Target dateTitle
11-Dec-2015End of analysis
15-Jan-2016Final paper delivered
29-Jan-2016Project closure
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
10.0 days
Activity this month
5.0 days
Activity this year
8.0 days
Activity to date
8.0 days
Estimate to complete current year
2.5 days
Estimate to complete future years
0.0 days

Project Info

Project
RIR Ltd systems review
Code
CSG009
Programme
CSG Portfolio Projects (OTHCSG)
Project Manager
Dawn Holmes
Project Sponsor
Charles Hill
Current Stage
Close
Status
Closed
Start Date
09-Oct-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
18-Mar-2016
Overall Priority
Normal
Category
Discretionary