A series of interviews have taken place with key stakeholders from RIR. ERI and EDINA
Issues
Issues securing confirmed interview dates due to previous diary commitments. This will impact the delivery & closure milestones by about 2 weeks which pushes them into the University shutdown period.
Next steps
Final interviews to be conducted
Draft technical report and analysis summary papers to be produced & shared with Project Sponsor