Report for November 2015
- Report Date
- November 2015
Achievements this period
- A series of interviews have taken place with key stakeholders from RIR. ERI and EDINA
Issues
- Issues securing confirmed interview dates due to previous diary commitments. This will impact the delivery & closure milestones by about 2 weeks which pushes them into the University shutdown period.
Next steps
- Final interviews to be conducted
- Draft technical report and analysis summary papers to be produced & shared with Project Sponsor
Target date | Title |
---|---|
11-Dec-2015 | End of analysis |
15-Jan-2016 | Final paper delivered |
29-Jan-2016 | Project closure |
- Approved budget
- 10.0 days
- Activity this month
- 5.0 days
- Activity this year
- 8.0 days
- Activity to date
- 8.0 days
- Estimate to complete current year
- 2.5 days
- Estimate to complete future years
- 0.0 days