Status report for October 2015
- Report Date
- October 2015
Achievements this period
- Approval received to start project
- Kick-off meeting held with Project Sponsor and Business Lead
- Draft Project Brief produced and curculated for review
- Resources secured
Issues
- None this period. Project is reported as GREEN
Next steps
- Interviews with key stakeholders
Target date | Title |
---|---|
06-Nov-2015 | End of planning |
27-Nov-2015 | End of analysis |
04-Dec-2015 | Final paper delivered |
11-Dec-2015 | Project closure |
- Approved budget
- 10.0 days
- Activity this month
- 1.5 days
- Activity this year
- 1.5 days
- Activity to date
- 1.5 days
- Estimate to complete current year
- 8.5 days
- Estimate to complete future years
- 0.0 days