January Report
- Report Date
- January 2015
Achievements in Last Period
- Deployment of Release 1 on 13th January for document upload facility functionality completed successfully
- Development Iteration 2 completed on 15th January
- Development Iteration 3 completed on 29th January
- Preparation for Release 2 deployment scheduled for 5th February
Issues
- PICCL raised to advise revised milestones due to removal of Dev Iteration 4 and return of 22 days to CSG Other Portfolio, as reviewed with Product Owner and Programme Manager.
- CF10 User Story delayed due to ITI UNIX resource on priority work, requested load balancer changes for 6th Feb for route to live environment and Release 3 deployment to live of 12th Feb
Next Steps
- Complete CF10 upgrades and Testing during Maintenance Iteration
- Preparation for Project Closure
- Approved budget
- 98.0 days
- Activity this month
- 33.0 days
- Activity this year
- 70.1 days
- Activity to date
- 70.1 days
- Estimate to complete current year
- 17.0 days
- Estimate to complete future years
- 0.0 days