January Report

Report Date
January 2015

Achievements in Last Period

  • Deployment of Release 1 on 13th January for document upload facility functionality completed successfully
  • Development Iteration 2 completed on 15th January
  • Development Iteration 3 completed on 29th January
  • Preparation for Release 2 deployment scheduled for 5th February

Issues

  • PICCL raised to advise revised milestones due to removal of Dev Iteration 4 and return of 22 days to CSG Other Portfolio, as reviewed with Product Owner and Programme Manager.
  • CF10 User Story delayed due to ITI UNIX resource on priority work, requested load balancer changes for 6th Feb for route to live environment and Release 3 deployment to live of 12th Feb

Next Steps

  • Complete CF10 upgrades and Testing during Maintenance Iteration
  • Preparation for Project Closure
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
98.0 days
Activity this month
33.0 days
Activity this year
70.1 days
Activity to date
70.1 days
Estimate to complete current year
17.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Enhancements for AIR
Code
CSG003
Programme
CSG Portfolio Projects (OTHCSG)
Project Manager
Karen Stirling
Project Sponsor
ALASTAIR Reid
Current Stage
Close
Status
Closed
Start Date
17-Oct-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
10-Mar-2015
Category
Discretionary