Report for July 2019
- Report Date
- June 2019
Achievements in Last Period
- UAT sign off agreed
- Deployment to LIVE
Issues
- None
Next Steps
- DSOR
- Closure
Milestones
| Deployment Sign Off Review (DSOR) | 08-Jul-2019 |
| Closure | 29-Jul-2019 |
- Approved budget
- 57.0 days
- Activity this month
- 18.0 days
- Activity this year
- 45.0 days
- Activity to date
- 45.0 days
- Estimate to complete current year
- 12.0 days
- Estimate to complete future years
- 0.0 days