Report for July 2019

Report Date
June 2019

Achievements in Last Period

  • UAT sign off agreed
  • Deployment to LIVE

Issues

  • None

Next Steps

  • DSOR
  • Closure

Milestones

Deployment Sign Off Review (DSOR) 08-Jul-2019
Closure 29-Jul-2019
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
57.0 days
Activity this month
18.0 days
Activity this year
45.0 days
Activity to date
45.0 days
Estimate to complete current year
12.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Annual Wiki Upgrade
Code
COM046
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Dawn Dodd
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
11-Jan-2019
Planning Date
29-Mar-2019
Delivery Date
26-Jun-2019
Close Date
29-Jul-2019
Overall Priority
Normal
Category
Compliance

Documentation