Report for May 2019
- Report Date
- May 2019
Achievements in Last Period
- Test upgrade completed
- Integration testing signed off
- UAT period has begun, ending on 14/06/2019. No issues have been reported so far.
Issues
- None
Next Steps
- UAT sign off agreed
- Deployment to LIVE
Milestones
| Acceptance sign off | 14-Jun-2019 |
| Deploy to LIVE | 26-Jun-2019 |
| Deployment Sign Off Review (DSOR) | 08-Jul-2019 |
| Closure | 29-Jul-2019 |
- Approved budget
- 57.0 days
- Activity this month
- 7.5 days
- Activity this year
- 21.5 days
- Activity to date
- 21.5 days
- Estimate to complete current year
- 32.5 days
- Estimate to complete future years
- 0.0 days