- Report Date
- January 2019
Achievements in Last Period
- Work has continued on the site migration and checking
- Agreement reached with the project team and key stakeholders to move out migration completion and closure milestones
- The project will report as GREEN although the milestones have moved out 6 weeks
Issues
Next steps
- Complete site migrations and checking.
- Approved budget
- 50.0 days
- Activity this month
- 1.7 days
- Activity this year
- 28.0 days
- Activity to date
- 56.0 days
- Estimate to complete current year
- 1.0 day
- Estimate to complete future years
- 0.0 days