Report for June 2017

Report Date
June 2017

Achievements

  • Project brief & planning completed

Issues

  • None

Next steps

  • Start upgrade.
  • Complete Build phase.
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
25.0 days
Activity this month
4.0 days
Activity this year
0.0 days
Activity to date
5.0 days
Estimate to complete current year
10.0 days
Estimate to complete future years
12.0 days

Project Info

Project
JIRA Upgrade 2017
Code
COM035
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Bill Lee
Current Stage
Close
Status
Closed
Start Date
06-Jun-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
11-Aug-2017
Programme Priority
4
Overall Priority
Normal
Category
Compliance

Documentation