Report for July 2017

Report Date
July 2017

Achievements this Period

  • UAT signed off
  • Load testing complete
  • Deployment to LIVE achieved
  • Closure report written and distributed
  • Deployment sign off achieved

Issues

  • Collaborative editing requires fixes, potentially to how we do the single sign on. Investigation is underway. This has been re-visited as there was budget to do this. If it can be done with minimal effort / disruption, then Collaborative Editing will be put Live on 09/08/18.
  • Closure date moved into August to allow for Collaborative Editing to be deployed

 

Next Steps

  • Deploy Collaborative Editing to TEST and LIVE
  • Closure

Milestones

18-Aug-2017 Project Closure
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
Change - Closure date moved to allow for Collaborative Editing to be deployed to TEST and LIVE. Agreed by project team and sponsor.
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Annual Wiki Upgrade
Code
COM034
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
10-Mar-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
08-Sep-2017
Programme Priority
6
Overall Priority
Normal
Category
Compliance

Documentation