Report for July 2017
- Report Date
- July 2017
Achievements this Period
- UAT signed off
- Load testing complete
- Deployment to LIVE achieved
- Closure report written and distributed
- Deployment sign off achieved
Issues
- Collaborative editing requires fixes, potentially to how we do the single sign on. Investigation is underway. This has been re-visited as there was budget to do this. If it can be done with minimal effort / disruption, then Collaborative Editing will be put Live on 09/08/18.
- Closure date moved into August to allow for Collaborative Editing to be deployed
Next Steps
- Deploy Collaborative Editing to TEST and LIVE
- Closure
Milestones
| 18-Aug-2017 | Project Closure |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days