Report for June 2017

Report Date
June 2017

Achievements this Period

  • UAT is currently being carried out with one issue being raised and resolved.
  • Request raised for out of hours working for Development Technology for the live install agreed by the resource manager
  • Deployment planed for the day

Issues

  • Collaborative editing requires fixes, potentially to how we do the single sign on. Investigation is underway. This is disabled for testing, and any changes will be applied to DEV. Not going LIVE with Collaborative Editing enabled, this will be enabled at a later date.
  • Project is AMBER as we are under budget

 

Next Steps

  • Sign off UAT
  • Complete load testing
  • Deploy to LIVE
  • Write and distribute closure report
  • Deployment sign off and Closure

 

Milestones

04-Jul-2017 Acceptance Sign off
11-Jul-2017 Deploy to LIVE
25-Jul-2017 Deployment sign off review
31-Jul-2017 Project Closure
Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
AMBER
RAG Commentary
Change: AMBER as the project is under budget as at the end of the Acceptance phase. Estimate to end has been revised and PICCL to be raised to return days to programme
Change Status
Activity
Approved budget
63.0 days
Activity this month
6.0 days
Activity this year
37.0 days
Activity to date
37.0 days
Estimate to complete current year
13.6 days
Estimate to complete future years
0.0 days

Project Info

Project
Annual Wiki Upgrade
Code
COM034
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
10-Mar-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
08-Sep-2017
Programme Priority
6
Overall Priority
Normal
Category
Compliance

Documentation