Report for May 2017
- Report Date
- May 2017
Achievements this Period
- DEV installation issue now resolved
- DEV sign off achieved
- Migration to TEST completed
- Integration testing completed
- Handed over for UAT for next 4 weeks.
Issues
- Collaborative editing requires fixes, potentially to how we do the single sign on. Investigation is underway. This is disabled for testing, and any changes will be applied to DEV.
Next Steps
- Any UAT issues will be resolved as they are logged.
- Request to be raised for out of hours working for Development Technology for the live install
- Collaborative editing issue fixed
- UAT signed off
Milestones
| 04-Jul-2017 | Acceptance Sign off |
| 11-Jul-2017 | Deploy to LIVE |
| 25-Jul-2017 | Deployment sign off review |
| 31-Jul-2017 | Project Closure |
- Approved budget
- 63.0 days
- Activity this month
- 10.0 days
- Activity this year
- 26.0 days
- Activity to date
- 26.0 days
- Estimate to complete current year
- 33.0 days
- Estimate to complete future years
- 0.0 days