Report for May 2017

Report Date
May 2017

Achievements this Period

  • DEV installation issue now resolved
  • DEV sign off achieved
  • Migration to TEST completed
  • Integration testing completed
  • Handed over for UAT for next 4 weeks.

Issues

  • Collaborative editing requires fixes, potentially to how we do the single sign on. Investigation is underway. This is disabled for testing, and any changes will be applied to DEV.

 

Next Steps

  • Any UAT issues will be resolved as they are logged.
  • Request to be raised for out of hours working for Development Technology for the live install
  • Collaborative editing issue fixed
  • UAT signed off

Milestones

04-Jul-2017 Acceptance Sign off
11-Jul-2017 Deploy to LIVE
25-Jul-2017 Deployment sign off review
31-Jul-2017 Project Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
63.0 days
Activity this month
10.0 days
Activity this year
26.0 days
Activity to date
26.0 days
Estimate to complete current year
33.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Annual Wiki Upgrade
Code
COM034
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
10-Mar-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
08-Sep-2017
Programme Priority
6
Overall Priority
Normal
Category
Compliance

Documentation