No progress was made in this period - a change to milestones is documented below
Issues
PICCL Change 7 - https://www.projects.ed.ac.uk/unpublished/project/com032/issues/7 , updated milestones, reported to WIS 30/6/17. The closure of this project requires to be rescheduled. This is due to a delay to fix the issue identified during UAT; automated emails to Service Management fail to be sent when a person opts out of the service (this requirement is documented in JIRA COM032-20).