Report for December 2017
- Report Date
- December 2017
Achievements
- LIVE build completed
- Acceptance signoff achieved
- LIVE delivery date approved
Issues
- none
Next Steps
- Deploy to LIVE
Milestones
| 16-Jan-2018 | Deliver |
| 30-Jan-2018 | Deployment review |
| 05-Feb-2018 | Close |
- Approved budget
- 120.0 days
- Activity this month
- 6.0 days
- Activity this year
- 28.0 days
- Activity to date
- 102.0 days
- Estimate to complete current year
- 18.0 days
- Estimate to complete future years
- 0.0 days