Report for December 2017

Report Date
December 2017

Achievements

  • LIVE build completed
  • Acceptance signoff achieved
  • LIVE delivery date approved

 Issues

  • none

 

Next Steps

  • Deploy to LIVE

 

Milestones

16-Jan-2018     Deliver
30-Jan-2018     Deployment review
05-Feb-2018     Close

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
120.0 days
Activity this month
6.0 days
Activity this year
28.0 days
Activity to date
102.0 days
Estimate to complete current year
18.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Serengeti Document Management Server Upgrade
Code
COM031
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Morna Findlay
Project Sponsor
Susan Cooke
Current Stage
Close
Status
Closed
Start Date
19-Sep-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
23-Mar-2018
Overall Priority
Normal
Category
Compliance