Report for August 2016
- Report Date
- August 2016
Report by Tim Gray for August 2016
Achievements in Last Period
- LIVE Upgrade completed
- LIVE Upgrade signed off
Issues
- No significant technical issues to report
- Due to the increased effort required to upgrade LIVE the project is 40 days over budget
Next Steps
- Move to closure
Project is AMBER due to budget overspend
- Approved budget
- 80.0 days
- Activity this month
- 29.0 days
- Activity this year
- 29.0 days
- Activity to date
- 118.0 days
- Estimate to complete current year
- 1.0 day
- Estimate to complete future years
- 0.0 days