Report for August 2016

Report Date
August 2016

Report by Tim Gray for August 2016

 

Achievements in Last Period

  • LIVE Upgrade completed
  • LIVE Upgrade signed off

Issues

  • No significant technical issues to report
  • Due to the increased effort required to upgrade LIVE the project is 40 days over budget

Next Steps

  • Move to closure

 

Project is AMBER due to budget overspend

Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
BLUE
Change Status
Activity
Approved budget
80.0 days
Activity this month
29.0 days
Activity this year
29.0 days
Activity to date
118.0 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days

Project Info

Project
Wiki Upgrade
Code
COM026
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
02-Feb-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Category
Compliance