Report for June 2016
- Report Date
- June 2016
Achievements in Last Period
- DEV review completed
- TEST migration to 12G completed
- TEST migration to new infrastructure completed
Issues
- A new issue with the application upgrade on TEST has been encountered and a call with Atlassian raised
Next Steps
- Upgrade application
- Complete load testing
- Complete UAT
- Deploy to LIVE
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days