Report for June 2016

Report Date
June 2016

Achievements in Last Period

  • DEV review completed
  • TEST migration to 12G completed
  • TEST migration to new infrastructure completed

Issues

  • A new issue with the application upgrade on TEST has been encountered and a call with Atlassian raised

Next Steps

  • Upgrade application
  • Complete load testing
  • Complete UAT
  • Deploy to LIVE
Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Wiki Upgrade
Code
COM026
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
02-Feb-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Category
Compliance