Report for May 206

Report Date
May 2016

Achievements in Last Period

  • TAD/Design signed off
  • DEV build continued
  • Project milestones replanned

Issues

  • Issue with DEV preventing peer testing has been opened with vendor

Next Steps

  • Build review
  • Build TEST infrastructure
  • Migrate TEST DB
  • Integration/load testing
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
78.0 days
Activity this month
20.0 days
Activity this year
52.0 days
Activity to date
52.0 days
Estimate to complete current year
36.0 days
Estimate to complete future years
3.0 days

Project Info

Project
Wiki Upgrade
Code
COM026
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
02-Feb-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Category
Compliance