April Report
- Report Date
- April 2016
Achievements in Last Period
- TAD completed
- DEV data migrated to new Oracle 12c infrastructure
- Agreement of 2 x new URL's for Genomics wiki
Issues
- No major issues to report
Next Steps
- Sign off TAD (design review)
- Build new development server
Milestones
Target date | Title |
---|---|
03-May-2016 | Design sign off (TAD) |
06-May-2016 | Build new DEV app server and install upgraded confuence |
02-Jun-2016 | Create test environment and migrate data |
23-Jun-2016 | Acceptance Sign off |
01-Jul-2016 | Deploy to Live |
18-Jul-2016 | DSOR |
28-Jul-2016 | Project Closure - sign off review |
- Approved budget
- 80.0 days
- Activity this month
- 9.2 days
- Activity this year
- 29.4 days
- Activity to date
- 29.4 days
- Estimate to complete current year
- 50.2 days
- Estimate to complete future years
- 0.0 days