April Report

Report Date
April 2016

Achievements in Last Period

  • TAD completed
  • DEV data migrated to new Oracle 12c infrastructure
  • Agreement of 2 x new URL's for Genomics wiki

 

Issues

  • No major issues to report

Next Steps

  • Sign off TAD (design review)
  • Build new development server

 

Milestones

Target dateTitle
03-May-2016Design sign off (TAD)
06-May-2016Build new DEV app server and install upgraded confuence
02-Jun-2016Create test environment and migrate data
23-Jun-2016Acceptance Sign off
01-Jul-2016Deploy to Live
18-Jul-2016DSOR
28-Jul-2016Project Closure - sign off review
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
80.0 days
Activity this month
9.2 days
Activity this year
29.4 days
Activity to date
29.4 days
Estimate to complete current year
50.2 days
Estimate to complete future years
0.0 days

Project Info

Project
Wiki Upgrade
Code
COM026
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
02-Feb-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Category
Compliance