March 2016

Report Date
March 2016

Achievements in Last Period

  • Agreement to add upgrade to Oracle now in Scope
  • Refresh of DEV & TEST databases completed
  • Agreement of dependency on INF110 to deliver Oracle 12c infrastructure

 

Issues

Next Steps

  • Migrate DEV data to new Oracle 12c infrastructure

 

Milestones

27-Apr-2016Migrate DATA to Oracle 12c DEV infrastructure
28-Apr-2016Build new DEV app server and install upgraded confluence
29-Apr-2016Recode IDM connector
02-Jun-2016Create test environment and migrate data
01-Jul-2016create live environment and migrate data
21-Jul-2016Delivery Sign off review
04-Aug-2016Project Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
80.0 days
Activity this month
14.4 days
Activity this year
18.4 days
Activity to date
18.4 days
Estimate to complete current year
61.4 days
Estimate to complete future years
0.0 days

Project Info

Project
Wiki Upgrade
Code
COM026
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
02-Feb-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Category
Compliance