Febraury 2016

Report Date
February 2016

Achievements in Last Period

  • Project Kick off with Business Lead & IS Apps DevTech.
  • Planning on going
  • Resources secured to deliver against majority of plan - negotiations on going

 

Issues

  • Upgrade project was estimated and approved at 50 days. Additional scope added to recode IDM connecter has added 8 days. Request to add Genomics migration has added another 20 days, meaning 78 days in total now required. Still to be agreed and approved.

Next Steps

  • Sign off brief and milestones

 

Milestones (to be planned)

Project Status
RAG Status
Time
GREEN
Cost
RED
Scope
RED
Overall
RED
Change Status
Activity
Approved budget
50.0 days
Activity this month
3.5 days
Activity this year
3.6 days
Activity to date
3.6 days
Estimate to complete current year
46.4 days
Estimate to complete future years
0.0 days

Project Info

Project
Wiki Upgrade
Code
COM026
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
02-Feb-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Category
Compliance