Febraury 2016
- Report Date
- February 2016
Achievements in Last Period
- Project Kick off with Business Lead & IS Apps DevTech.
- Planning on going
- Resources secured to deliver against majority of plan - negotiations on going
Issues
- Upgrade project was estimated and approved at 50 days. Additional scope added to recode IDM connecter has added 8 days. Request to add Genomics migration has added another 20 days, meaning 78 days in total now required. Still to be agreed and approved.
Next Steps
- Sign off brief and milestones
Milestones (to be planned)
- Approved budget
- 50.0 days
- Activity this month
- 3.5 days
- Activity this year
- 3.6 days
- Activity to date
- 3.6 days
- Estimate to complete current year
- 46.4 days
- Estimate to complete future years
- 0.0 days