October 2015
- Report Date
- October 2015
DSOR and closure were delayed by request of Project Sponsor to allow content to be added by IS Corporate and launch site to IS Staff.
Achievements in Last Period
- DSOR approved.
- Service Management Team Manager agreed responsibilities for support with Applications Management (documented in Deployment Checklist with link to OLA).
- Closure review completed and approved.
- Project closure approved.
Issues
- No outstanding issues.
Next Steps
- None
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days