September 2015
- Report Date
- September 2015
Site was completed and delivered to schedule - launch to IS Staff is pending content addition by IS Corporate and IS Divisional champions, led by Change Manager.
Achievements in Last Period
- Service Management Team Manager (on behalf of Senior Supplier) and PM met with Change Manager to ensure no post deployment snagging for site launch.
Issues
- No major issues.
- DSOR and closure rescheduled at request of Project Sponsor until after formal launch to IS Staff. This was later than anticipated
- Change Manager indicated launch would take place w/c 14/09 but this was delayed until w/c 28/09 which pushed the DSOR back.
Next Steps
- DSOR.
- Closure.
- Approved budget
- 25.0 days
- Activity this month
- 3.6 days
- Activity this year
- 15.4 days
- Activity to date
- 20.6 days
- Estimate to complete current year
- 1.0 day
- Estimate to complete future years
- 0.0 days