Report for March 2016
- Report Date
- March 2016
Achievements in Last Period
- Testing competed for outstanding security (new FW rule)
Issues
- Delay in getting FW implementedĀ on LIVE
- Delay in testing on TEST due to staff illness
Next Steps
- Implement FW rule on LIVEĀ
- Deployment Review
- Closure
- Approved budget
- 170.0 days
- Activity this month
- 1.0 day
- Activity this year
- 37.0 days
- Activity to date
- 168.0 days
- Estimate to complete current year
- 2.0 days
- Estimate to complete future years
- 0.0 days