Report for February 2016

Report Date
February 2016

Achievements in Last Period

  • Solution for security issue JIRA-25 implemented on DEV and TEST

Issues

  • No new issues

Next Steps

  • Complete testing and implement on LIVE
  • Deployment Review
  • Closure

 

Milestones

18-Mar-2016 Deployment Review
25-Mar-2016 Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
170.0 days
Activity this month
0.0 days
Activity this year
36.0 days
Activity to date
167.0 days
Estimate to complete current year
3.0 days
Estimate to complete future years
0.0 days

Project Info

Project
BI Additional Tools - Dashboards/Report
Code
COM015
Programme
ISG - Communication (COM)
Project Manager
Tim Gray
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
21-Aug-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Apr-2016
Category
Discretionary