Report for January 2016

Report Date
January 2016

Achievements in Last Period

  • Solution for security issue JIRA-25 agreed awiting implementaion and testing

Issues

  • No new issues

Next Steps

  • Implement solution for security issue
  • Deployment Review
  • Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
170.0 days
Activity this month
1.0 day
Activity this year
35.0 days
Activity to date
165.0 days
Estimate to complete current year
4.0 days
Estimate to complete future years
0.0 days

Project Info

Project
BI Additional Tools - Dashboards/Report
Code
COM015
Programme
ISG - Communication (COM)
Project Manager
Tim Gray
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
21-Aug-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Apr-2016
Category
Discretionary