Report for August 2015
- Report Date
- August 2015
Achievements in Last Period
- UAT successfully completed
- Solution deployed to LIVE
- Estimate to complete revised
- Milestones revised
Issues
- RMAS connection issue passed over to RMAS Team (Jamie Thin)
Next Steps
- Clarify scope, what remains outstanding
- Complete outstanding work
- Enable 360 Eyes Auditing on LIVE
- Deployment Review
- Move to closure
- Approved budget
- 149.0 days
- Activity this month
- 10.0 days
- Activity this year
- 10.0 days
- Activity to date
- 140.0 days
- Estimate to complete current year
- 12.5 days
- Estimate to complete future years
- 0.0 days