Report for July 2015

Report Date
July 2015

Achievements in Last Period

  • New solution employing shared secret to create a trusted connection has been verified successfully on Dev and Test environments.

 

Issues

  • Connection problem specifically with RMAS data; this has delayed acceptance and deployment to the live environment, but Business Manager is confident that this can be resolved with DevTech assistance and therefore recommends deploying overall solution to Live while this is looked into.

 

Next Steps

  • Acceptance and Deployment.

 

Milestones

24-Jul-2015Acceptance ReviewAccept
27-Jul-2015DeploymentDeliver
14-Aug-2015DSORDeliver
28-Aug-2015ClosureClose

 

NB Milestones to be replanned due to unavailability of Business Manager and Technical Architect 07/08/15 to 21/08/15.

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
140.0 days
Activity this month
7.0 days
Activity this year
131.0 days
Activity to date
131.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
8.0 days

Project Info

Project
BI Additional Tools - Dashboards/Report
Code
COM015
Programme
ISG - Communication (COM)
Project Manager
Tim Gray
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
21-Aug-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Apr-2016
Category