Report for July 2015
- Report Date
- July 2015
Achievements in Last Period
- New solution employing shared secret to create a trusted connection has been verified successfully on Dev and Test environments.
Issues
- Connection problem specifically with RMAS data; this has delayed acceptance and deployment to the live environment, but Business Manager is confident that this can be resolved with DevTech assistance and therefore recommends deploying overall solution to Live while this is looked into.
Next Steps
- Acceptance and Deployment.
Milestones
| 24-Jul-2015 | Acceptance Review | Accept |
| 27-Jul-2015 | Deployment | Deliver |
| 14-Aug-2015 | DSOR | Deliver |
| 28-Aug-2015 | Closure | Close |
NB Milestones to be replanned due to unavailability of Business Manager and Technical Architect 07/08/15 to 21/08/15.
- Approved budget
- 140.0 days
- Activity this month
- 7.0 days
- Activity this year
- 131.0 days
- Activity to date
- 131.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 8.0 days