Report for May 2015

Report Date
May 2015

Achievements in Last Period

  • Identification of potential authentication solutions as alternative to cosign based approach.
  • Discussion with Influential about feasible options in the timeline required to deliver a crystal reports sharing solution for RMAS.

Issues

  • Behaviour of EASE configuration on TEST different to DEV, and intermittent connectivity issues on the new DEV environment, led to discussion between Business Manager and Development Technology. Development Technology are now not confident of resolving the legacy issues on the platform and delivering a reliable solution using the current technology. Technical approach is being reviewed.
  • It was acknowleged that there needs to be a solution in place to deliver sharing crystal reports for RMAS ahead of UAT (Aug 2015). Head of Project Services has been alerted to this issue.
  • If delivering reliable end-user access proves impractical via EASE then that will not be delivered within the scope of this project but will be considered as part of a wider strategic approach.

 

Next Steps

  • Agree revised approach and milestones with Project Sponsor.
  • Deliver revised plan, focussing on solution which RMAS can use.

 

05-May-2015Phase 1: Apply infrastructure changesDeliver
08-May-2015Phase 1: Technical Deployment ReviewExecute
19-Jun-2015Phase 2: Build ReviewBuild
26-Jun-2015Phase 2: Integration ReviewIntegrate
03-Jul-2015Phase 2: Acceptance ReviewAccept
10-Jul-2015Phase 2: Deployment ReviewDeliver
17-Jul-2015Phase 2: DeliveryDeliver
31-Jul-2015ClosureClose

 

 

Project Status
RAG Status
Time
RED
Cost
RED
Scope
AMBER
Overall
AMBER
Change Status
Activity
Approved budget
120.0 days
Activity this month
7.5 days
Activity this year
116.8 days
Activity to date
116.8 days
Estimate to complete current year
2.1 days
Estimate to complete future years
0.0 days

Project Info

Project
BI Additional Tools - Dashboards/Report
Code
COM015
Programme
ISG - Communication (COM)
Project Manager
Tim Gray
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
21-Aug-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Apr-2016
Category
Discretionary