Report for March 2015
- Report Date
- March 2015
Achievements this Period
- Build stage signed off
- List of MVM sites and databases to be added to new infrastructure (under MVM002) agreed
- CF10 licence agreed with Production Management
- Approach to migrations clarified
Issues
- Build of LIVE servers delayed
- Problem with Cosign & Plesk reported - still being investigated
Next Steps
- LIVE servers being finalised
- Integration tests to be carried out
- Plans for migrations to be completed
Milestones
| 15-Apr-2015 | Integration sign-off | Integrate |
| 29-Apr-2015 | Acceptance sign-off | Accept |
| 04-May-2015 | Commence migrations to LIVE (Deployment milestone) | Deliver |
| 09-Jul-2015 | Deployment sign-off | Deliver |
| 17-Jul-2015 | Project closure | Close |
- Approved budget
- 161.0 days
- Activity this month
- 27.2 days
- Activity this year
- 87.3 days
- Activity to date
- 87.3 days
- Estimate to complete current year
- 73.7 days
- Estimate to complete future years
- 0.0 days