Report for March 2015

Report Date
March 2015

Achievements this Period

  • Build stage signed off
  • List of MVM sites and databases to be added to new infrastructure (under MVM002) agreed
  • CF10 licence agreed with Production Management
  • Approach to migrations clarified

Issues

  • Build of LIVE servers delayed 
  • Problem with Cosign & Plesk reported - still being investigated

Next Steps

  • LIVE servers being finalised
  • Integration tests to be carried out
  • Plans for migrations to be completed

 

Milestones

15-Apr-2015Integration sign-offIntegrate
29-Apr-2015Acceptance sign-offAccept
04-May-2015Commence migrations to LIVE (Deployment milestone)Deliver
09-Jul-2015Deployment sign-offDeliver
17-Jul-2015Project closureClose

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
161.0 days
Activity this month
27.2 days
Activity this year
87.3 days
Activity to date
87.3 days
Estimate to complete current year
73.7 days
Estimate to complete future years
0.0 days

Project Info

Project
Update and Rationalise Windows Web Hosting
Code
COM014
Programme
ISG - Communication (COM)
Project Manager
David Watters
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
25-Aug-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
21-Aug-2015
Category
Discretionary