Report for February 2015

Report Date
February 2015

Achievements this Period

  • Plesk software fully configured and tested
  • Test migrations carried out with Plesk on new server
  • List of sites and databases to be migrated completed

Issues

  • None reported

Next Steps

  • Migration steps to be finalised
  • LIVE servers being finalised
  • Plans for migrations to be completed

 

Milestones

11-Mar-2015Build stage sign-offBuild
15-Apr-2015Integration sign-offIntegrate
29-Apr-2015Acceptance sign-offAccept
04-May-2015Commence migrations to LIVE (Deployment milestone)Deliver
09-Jul-2015Deployment sign-offDeliver
17-Jul-2015Project closureClose

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
161.0 days
Activity this month
14.1 days
Activity this year
59.9 days
Activity to date
59.9 days
Estimate to complete current year
101.6 days
Estimate to complete future years
0.0 days

Project Info

Project
Update and Rationalise Windows Web Hosting
Code
COM014
Programme
ISG - Communication (COM)
Project Manager
David Watters
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
25-Aug-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
21-Aug-2015
Category
Discretionary