Report for February 2015
- Report Date
- February 2015
Achievements this Period
- Plesk software fully configured and tested
- Test migrations carried out with Plesk on new server
- List of sites and databases to be migrated completed
Issues
- None reported
Next Steps
- Migration steps to be finalised
- LIVE servers being finalised
- Plans for migrations to be completed
Milestones
| 11-Mar-2015 | Build stage sign-off | Build |
| 15-Apr-2015 | Integration sign-off | Integrate |
| 29-Apr-2015 | Acceptance sign-off | Accept |
| 04-May-2015 | Commence migrations to LIVE (Deployment milestone) | Deliver |
| 09-Jul-2015 | Deployment sign-off | Deliver |
| 17-Jul-2015 | Project closure | Close |
- Approved budget
- 161.0 days
- Activity this month
- 14.1 days
- Activity this year
- 59.9 days
- Activity to date
- 59.9 days
- Estimate to complete current year
- 101.6 days
- Estimate to complete future years
- 0.0 days