Report for December 2014
- Report Date
- December 2014
Achievements this Period
- Listing of sites/databases to be migrated drafted by Service Management
- TAD reviewed and signed off
- Servers delivered by ITI
- Server build completed by Development Technology
Issues
- None reported
Next Steps
- Plesk software to be acquired and implemented
- Test migrations to be started
- Migration process to be documented
Milestones
| 11-Mar-2015 | Build stage sign-off | Build |
| 15-Apr-2015 | Integration sign-off | Integrate |
| 29-Apr-2015 | Acceptance sign-off | Accept |
| 04-May-2015 | Commence migrations to LIVE (Deployment milestone) | Deliver |
| 09-Jul-2015 | Deployment sign-off | Deliver |
| 17-Jul-2015 | Project closure | Close |
- Approved budget
- 161.0 days
- Activity this month
- 12.1 days
- Activity this year
- 27.6 days
- Activity to date
- 27.6 days
- Estimate to complete current year
- 132.9 days
- Estimate to complete future years
- 0.0 days