Report for November 2014

Report Date
November 2014

Achievements this Period

  • Terms of Reference approved by WIS
  • TAD drafted and issued for peer review
  • Server order started
  • Listing of sites/databases to be migrated under preparation

Issues

  • None reported

Next Steps

  • TAD to be signed off
  • Server order to be submitted
  • Design Stage sign-off
  • Server build to commence

 

Milestones

09-Dec-2014Systems design sign-offAnalyse
11-Mar-2015Build stage sign-offBuild
15-Apr-2015Integration sign-offPlan
29-Apr-2015Acceptance sign-offAccept
04-May-2015Commence migrations to LIVE (Deployment milestone)Deliver
09-Jul-2015Deployment sign-offDeliver
17-Jul-2015Project closureClose

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
161.0 days
Activity this month
5.7 days
Activity this year
14.7 days
Activity to date
14.7 days
Estimate to complete current year
145.3 days
Estimate to complete future years
0.0 days

Project Info

Project
Update and Rationalise Windows Web Hosting
Code
COM014
Programme
ISG - Communication (COM)
Project Manager
David Watters
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
25-Aug-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
21-Aug-2015
Category
Discretionary