Report for November 2014
- Report Date
- November 2014
Achievements this Period
- Terms of Reference approved by WIS
- TAD drafted and issued for peer review
- Server order started
- Listing of sites/databases to be migrated under preparation
Issues
- None reported
Next Steps
- TAD to be signed off
- Server order to be submitted
- Design Stage sign-off
- Server build to commence
Milestones
| 09-Dec-2014 | Systems design sign-off | Analyse |
| 11-Mar-2015 | Build stage sign-off | Build |
| 15-Apr-2015 | Integration sign-off | Plan |
| 29-Apr-2015 | Acceptance sign-off | Accept |
| 04-May-2015 | Commence migrations to LIVE (Deployment milestone) | Deliver |
| 09-Jul-2015 | Deployment sign-off | Deliver |
| 17-Jul-2015 | Project closure | Close |
- Approved budget
- 161.0 days
- Activity this month
- 5.7 days
- Activity this year
- 14.7 days
- Activity to date
- 14.7 days
- Estimate to complete current year
- 145.3 days
- Estimate to complete future years
- 0.0 days