Report for October 2014

Report Date
October 2014

Achievements this Period

  • Terms of Reference prepared for submission to WIS
  • Further meetings with stakeholders to establish scope/approachof project
  • Follow-up estimation discussions held with stakeholders

Issues

  • Planning sign-off moved because of sickness absence and leave (PM)

Next Steps

  • Terms of Reference to be submitted to WIS
  • Work to commence on TAD
  • Specification and order of replacement servers to be carried out

 

Milestones

07-Nov-2014Planning sign-offPlan

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
200.0 days
Activity this month
4.9 days
Activity this year
9.0 days
Activity to date
9.0 days
Estimate to complete current year
191.4 days
Estimate to complete future years
0.0 days

Project Info

Project
Update and Rationalise Windows Web Hosting
Code
COM014
Programme
ISG - Communication (COM)
Project Manager
David Watters
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
25-Aug-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
21-Aug-2015
Category
Discretionary