Report for September 2014
- Report Date
- September 2014
Achievements in Last Period
- Project website set up
- Initial meeting with Service Management to discuss what needs to be included in project
- Work started on ToR
Issues
- Planning sign-off moved because of difficulties in getting meeting arranged (due to leave & training)
Next Period
- Project brief to be submitted to WIS
- Work to start on 'proof of concept' for migrating older sites & databases
Milestones
| 17-Oct-2014 | Planning sign-off | Plan |
- Approved budget
- 200.0 days
- Activity this month
- 4.1 days
- Activity this year
- 4.1 days
- Activity to date
- 4.1 days
- Estimate to complete current year
- 195.9 days
- Estimate to complete future years
- 0.0 days