Report for June 2015

Report Date
June 2015

Achievements this Period

  • TEST service - servers built and tested. Test migrations completed and signed off.
  • Acceptance sign-off submitted.
  • LIVE service - some databases already migrated successfully.
  • LIVE server ready - awaiting application of CF10 licence 

Issues

  • CF10 licence had to be renegotiated with Adobe (delayed sign-off planned for 15/05)

Next Steps

  • Database migrations to be completed
  • LIVE migrations of websites to commence
  • Prokect completion to commence

 

Milestones

 

15-Jun-2015Commence migrations to LIVE (Deployment milestone)Deliver
23-Jul-2015Deployment sign-offDeliver
31-Jul-2015Project closureClose
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
141.0 days
Activity this month
14.0 days
Activity this year
132.8 days
Activity to date
132.8 days
Estimate to complete current year
8.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Update and Rationalise Windows Web Hosting
Code
COM014
Programme
ISG - Communication (COM)
Project Manager
David Watters
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
25-Aug-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
21-Aug-2015
Category
Discretionary