Report for June 2015
- Report Date
- June 2015
Achievements this Period
- TEST service - servers built and tested. Test migrations completed and signed off.
- Acceptance sign-off submitted.
- LIVE service - some databases already migrated successfully.
- LIVE server ready - awaiting application of CF10 licence
Issues
- CF10 licence had to be renegotiated with Adobe (delayed sign-off planned for 15/05)
Next Steps
- Database migrations to be completed
- LIVE migrations of websites to commence
- Prokect completion to commence
Milestones
| 15-Jun-2015 | Commence migrations to LIVE (Deployment milestone) | Deliver |
| 23-Jul-2015 | Deployment sign-off | Deliver |
| 31-Jul-2015 | Project closure | Close |
- Approved budget
- 141.0 days
- Activity this month
- 14.0 days
- Activity this year
- 132.8 days
- Activity to date
- 132.8 days
- Estimate to complete current year
- 8.5 days
- Estimate to complete future years
- 0.0 days