Report for October 2013

Report Date
October 2013
  • Achievements in Last Period

Design and build of Phase 1 Deliverables completed.

Peer testing and JIRA fixing in progress on IDM and UI builds.

New Dev VM created to house UI and eventually Grouper.

BRD for Phase 2 reviewed

Issues

Milestones will be re-planned due to additional Dev Tech estimates.

Scope for Phase 2 still in discussion.

  • Next Steps

Re-plan milestones for ongoing and subsequent phases.

Complete sign off of BRD for Phase 2 and 3.

Normalise project sign off milestones after annual leave of team members.

BRD documents for phase 3 to be reviewed and signed off.

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
361.0 days
Activity this month
26.0 days
Activity this year
90.0 days
Activity to date
154.0 days
Estimate to complete current year
206.0 days
Estimate to complete future years
0.0 days