Report for August 2013

Report Date
August 2013
  • Achievements in Last Period

BRD documents for phases 2 and 3 under review.

Detailed design prepared for Phase 1

Build preparation in progress for Phase 1

Issues

High level design for phases 1  to 4 updated with comments from review and re- circulated. Still to be signed off.

  • Next Steps

Formal sign off of the high Level design will be achieved.

Circulate , review and sign off detailed design for Phase 1

BRD documents for phases 2 and 3 to be reviewed and signed off.

 

Target dateTitle
28-Jun-2013Brief Sign Off
31-Jul-2013Phase 1 Push - Initiate BRD sign off
06-Aug-2013Phase 1 Push - Design sign Off
09-Sep-2013Phase 2 Inbound - Initiate
27-Sep-2013Phase 1 Push - Build sign Off
03-Oct-2013Phase 1 Push - ASOR
04-Oct-2013Phase 2 Inbound - Design Sign Off
09-Oct-2013Phase 1 Push - Deploy
16-Oct-2013Phase 3 Pull - Initiate
16-Oct-2013Phase 1 Push - DSOR/Closure
06-Dec-2013Phase 2 Inbound - Build Sign Off
17-Dec-2013Phase 3 Pull - Design Sign Off
08-Jan-2014Phase 2 Inbound - ASOR
09-Jan-2014Phase 2 Inbound - Deploy
10-Jan-2014Phase 4 Grouper - Initiate
14-Jan-2014Phase 4 Grouper - Design Sign Off
16-Jan-2014Phase 2 Inbound - DSOR/Closure
20-Jan-2014Phase 3 Pull - Build Sign Off
03-Feb-2014Phase 3 Pull - ASOR
04-Feb-2014Phase 4 Grouper - Build Sign Off
07-Feb-2014Phase 3 Pull - Deploy
14-Feb-2014Phase 3 Pull - DSOR/Closure
21-Feb-2014Phase 4 Grouper - ASOR
24-Feb-2014Phase 4 Grouper - Deploy
28-Feb-2014Phase 4 Grouper - DSOR/Closure
14-Mar-2014COM007 - Project Closure

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
331.0 days
Activity this month
23.0 days
Activity this year
23.0 days
Activity to date
87.0 days
Estimate to complete current year
243.0 days
Estimate to complete future years
0.0 days