Report for July 2013

Report Date
July 2013
  • Achievements in Last Period

Establishment of Project Board , meetings arranged.

PM continued discussions with Service Management and Technical Leads.

High level design for phases 1  to 4 updated with comments from review and re- circulated.

KPI data will be included in the design for Phase 1 but no reporting or interpretation of the figures will in included in Phase 1.

BRD for Phase 1 completed and signed off.

Issues

Resources have been diverted to other projects and work , affecting milestones.

  • Next Steps

Formal sign off of the high Level design will be achieved.

BRD documents for phases 2 and 3 to be reviewed and signed off.

 

Target dateTitle
28-Jun-2013Brief Sign Off
31-Jul-2013Phase 1 Push - Initiate BRD sign off
01-Aug-2013Phase 2 Inbound - Initiate
06-Aug-2013Phase 1 Push - Design sign Off
22-Aug-2013Phase 2 Inbound - Design Sign Off
20-Sep-2013Phase 1 Push - Build sign Off
02-Oct-2013Phase 1 Push - DSOR/Closure
03-Oct-2013Phase 1 Push - ASOR
04-Oct-2013Phase 1 Push - Deploy
21-Oct-2013Phase 3 Pull - Initiate
05-Nov-2013Phase 2 Inbound - Build Sign Off
11-Nov-2013Phase 3 Pull - Design Sign Off
14-Nov-2013Phase 2 Inbound - ASOR
15-Nov-2013Phase 2 Inbound - Deploy
19-Nov-2013Phase 2 Inbound - DSOR/Closure
20-Jan-2014Phase 4 Grouper - Initiate
03-Feb-2014Phase 4 Grouper - Design Sign Off
06-Feb-2014Phase 3 Pull - ASOR
07-Feb-2014Phase 3 Pull - Deploy
14-Feb-2014Phase 3 Pull - DSOR/Closure
06-Mar-2014Phase 4 Grouper - Build Sign Off
07-Mar-2014Phase 3 Pull - Build Sign Off
27-Mar-2014Phase 4 Grouper - ASOR
28-Mar-2014Phase 4 Grouper - Deploy
03-Apr-2014Phase 4 Grouper - DSOR/Closure
17-Apr-2014COM007 - Project Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
331.0 days
Activity this month
8.7 days
Activity this year
56.0 days
Activity to date
56.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
265.0 days