March Report

Report Date
March 2015

Achievements in Last Period

  • COM007-165 - JIRA now resolved IDM UI Server restart completed and handover documentation to Production Supoprt completed for Grouper - Deployment Review sign off completed
  • Updates added Overall Project Closure Report
  • Lessons Learnt session held with project team

Issues

  • At Lessons Learnt session Project Sponsor advised that project cannot be closed until issues with IDM Dashboard had been resolved in Live although originally agreed that any other activity other than development was to be completed via support
    • PICCL raised to provide plan of action for IDM Dashboard activity
    • Advise placeholder closure milestone for end of April
    • Estimate effort to fix outstanding JIRAs raised via IDM001
    • Possible resource conflict for PM and Developer time as allocatred to priority 1 project
    • Approval required for additional funding therefore discussion between project sponsor and prohramme manager required

Next Steps

  • Resolve oustanding JIRAs for Dashboard
  • Complete and sign off testing
  • Deploy to live
  • Completion report finalised and Closure milestone signed off

 

The project status is marked as AMBER      

 

30-Apr-2015

COM007 - Project Closure

 

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
AMBER
Overall
AMBER
Change Status
Activity
Approved budget
627.0 days
Activity this month
3.4 days
Activity this year
100.5 days
Activity to date
633.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days