Report for May 2013
- Report Date
- May 2013
- Achievements in Last Period
PM continued discussions with Service Management and Technical Leads.
Agreement reached on scope and VRS is not part of the core project phases.
Development team have been working on the high level design.
Grouper upgrade Options document circluated for review and discussion.
Student sync completion work in progress
- Next Steps
Complete Brief for circulation and sign off.
| Target date | Title |
|---|---|
| 07-Jun-2013 | Brief Completion |
- Approved budget
- 331.0 days
- Activity this month
- 14.3 days
- Activity this year
- 14.3 days
- Activity to date
- 14.3 days
- Estimate to complete current year
- 76.7 days
- Estimate to complete future years
- 240.0 days