July Report
- Report Date
- July 2014
Achievements in Last Period
- Phase 2 Inbound ASOR sign off completed
- Phase 2 Inbound Deployed 16/17th July successfully no impact from essential core maintenance completed 15th July nor ITS103 deployment over same period
- Phase 2 Inbound DSOR / Closure sign off completed
- Phase 3A Pull Services and Upgrade Grouper Design Review held, 1 remaining sign off to be achieved by Tech Management
Issues
- ORACLE patch upgrade to 11.1.1.7.3 completed via Support Team on DEV SOA however problems being encountered with known bug identified – causing system to run slower for notifications. Review actions to resolve issue as due to commence Phase 3A build activity and only limited period available to upgrade patch on Live due to change freeze commencing 18th August
- Database Migration dates to be agreed on review of remaining budget.
Next Steps
- Phase 3A Build activity and environment builds
- Information gathering for potential database migration work to allow further estimation of effort for additional budget approval
05-Sep-14 Phase 3A Pull Services & Upgrade Grouper - Build Sign Off (placeholder)
10-Oct-14 Phase 3A Pull Services & Upgrade Grouper - ASOR (placeholder)
24-Oct-14 Phase 3A Pull Services & Upgrade Grouper - Deploy (placeholder)
07-Nov-14 Phase 3A Pull Services & Upgrade Grouper - DSOR/Closure (placeholder)
TBC IDM Database Migration - Initiate
TBC IDM Database Migration - Design Sign Off
TBC IDM Database Migration - Build Sign Off
TBC IDM Database Migration – Migrate Dev completed
TBC IDM Database Migration – Migrate Test completed
TBC IDM Database Migration – Migrate Live completed
TBC IDM Database Migration – DSOR/Closure
TBC COM007 - Project Closure
- Approved budget
- 601.0 days
- Activity this month
- 29.6 days
- Activity this year
- 469.0 days
- Activity to date
- 532.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 77.6 days