July Report

Report Date
July 2014

Achievements in Last Period

  • Phase 2 Inbound ASOR sign off completed
  • Phase 2 Inbound Deployed 16/17th July successfully no impact from essential core maintenance completed 15th July nor ITS103 deployment over same period
  • Phase 2 Inbound DSOR / Closure sign off completed
  • Phase 3A Pull Services and Upgrade Grouper Design Review held, 1 remaining sign off to be achieved by Tech Management

             

Issues

  • ORACLE patch upgrade to 11.1.1.7.3 completed via Support Team on DEV SOA however problems being encountered with known bug identified – causing system to run slower for notifications. Review actions to resolve issue as due to commence Phase 3A build activity and only limited period available to upgrade patch on Live due to change freeze commencing 18th August
  • Database Migration dates to be agreed on review of remaining budget.

      

Next Steps

  • Phase 3A Build activity and environment builds
  • Information gathering for potential database migration work to allow further estimation of effort for additional budget approval

 

05-Sep-14  Phase 3A Pull Services & Upgrade Grouper - Build Sign Off (placeholder)

10-Oct-14   Phase 3A Pull Services & Upgrade Grouper - ASOR (placeholder)

24-Oct-14   Phase 3A Pull Services & Upgrade Grouper - Deploy (placeholder)

07-Nov-14  Phase 3A Pull Services & Upgrade Grouper - DSOR/Closure (placeholder)

TBC        IDM Database Migration - Initiate           

TBC        IDM Database Migration - Design Sign Off             

TBC        IDM Database Migration - Build Sign Off 

TBC        IDM Database Migration – Migrate Dev completed            

TBC        IDM Database Migration – Migrate Test completed            

TBC        IDM Database Migration – Migrate Live completed

TBC        IDM Database Migration – DSOR/Closure             

TBC        COM007 - Project Closure

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
601.0 days
Activity this month
29.6 days
Activity this year
469.0 days
Activity to date
532.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
77.6 days