Migrate IDM to Oracle SOA Suite 11g and Upgrade Grouper - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
April 2015 BLUE 641.0 days 639.8 days 0.0
Content
Status
Closed
Current Stage
Close
Start Date
Wednesday, 27 March 2013
Close Date
Friday, 8 May 2015
Project information
Project Code
COM007
Programme
ISG - Communication (COM)
Session
14/15
Organisational Unit
IS Applications
Project Category
Compliance
Programme Priority
2