Report for October 2012

Report Date
October 2012

Achievements in Last Period

  • The Project Board has reviewed the final report submitted by Delloite. 
  • Changes to the report are required before it is sent to stakeholders.
  • The report will be taken to KSC on Friday 16th November.
  • After the KSC meeting, the report will be distributed wider.

 

Issues

  • Remaining milestones revised in line with timescales for KSC meeting.

Next Steps

  • Report distribution.
  • Project closure.

 

Target dateTitle
16-Nov-2012Acceptance of Discovery Report
19-Nov-2012Release of Discovery Report
23-Nov-2012Closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Business Intelligence Needs Analysis - Discovery Phase
Code
COM003
Programme
Z. Communication, Media and Web (CMW) (Closed 31/07/14)
Project Manager
Adam Wadee
Project Sponsor
Dorothy Miell
Current Stage
Close
Status
Closed
Start Date
11-Jul-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
14-Dec-2012
Programme Priority
2
Overall Priority
Normal

Documentation