Report for October 2014
- Report Date
- October 2014
Report by Tim Gray for October 2014
Achievements
- Integration testing completed
- UAT completed
- LIVE Upgrade completed
Issues
- An on going SSL issue forced the deployment to be brought forward by 2 weeks. This reduced UAT period to only a few days but thanks to significant effort from Hugh Brown and business partners, UAT was completed. The LIVE upgrade did take longer than planned due to longer running scripts. This resulted in a 5 day outage not the 3 days originally planned.
Next Steps
- Deployment review
- Close project
- Approved budget
- 86.0 days
- Activity this month
- 19.8 days
- Activity this year
- 35.1 days
- Activity to date
- 99.6 days
- Estimate to complete current year
- 3.7 days
- Estimate to complete future years
- 0.0 days