Report for June 2014
- Report Date
- June 2014
Achievements in Last Period
- Serengeti's TEST upgrade completed
- TEST configuration
Issues
- A showstopper with the EBIS integration has not yet been resolved.
- Agreement not yet reached with E&B or confirmed with Finance for revised LIVE upgrade (21/07/14)
- Integration sign off delayed due to upgrade and post upgrade configuration issues
- LIVE upgrade moved out due to other higher prioritised work (APPS LIVE DB Migration and IDM Upgrade)
Next Steps
- Compete Integration testing
- Complete UAT
- Upgrade LIVE now w/c 21/07/14. Milestones to be re-planned when Serengeti confirm date
Project status amended to AMBER due to unresolved issues
- Approved budget
- 86.0 days
- Activity this month
- 11.0 days
- Activity this year
- 59.0 days
- Activity to date
- 59.0 days
- Estimate to complete current year
- 26.0 days
- Estimate to complete future years
- 2.0 days