Report for April 2014

Report Date
April 2014

Achievements in Last Period

  • DEV upgrade continued

 Issues

  • There are some issues with the application URL and co-sign module, which are being addressed with Serengeti

Next Steps

  • Compete DEV build
  • TEST upgrade

 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
86.0 days
Activity this month
11.0 days
Activity this year
31.0 days
Activity to date
31.0 days
Estimate to complete current year
55.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Upgrade Document Management System
Code
CMW010
Programme
ISG - Communication (COM)
Project Manager
Tim Gray
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
03-Feb-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Category
Compliance