Report for March 2014

Report Date
March 2014

Achievements in Last Period

  • Preparation completed for DEV upgrade

 Issues

  • During the first steps of the upgrade a DB issue arose that prevented the CMSDK scripts from completing. Serengeti have identified how this can be fixed but due to availability issues this cannot be scheduled until the week commencing 21/04/14 (to be confirmed).

Next Steps

  • Confirmation of revised milestones
  • Re do DB prep ahead of DEV upgrade
  • Upgrade DEV

 

Project marked Amber as date not yet confirmed by Serengeti

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
86.0 days
Activity this month
11.5 days
Activity this year
18.0 days
Activity to date
18.0 days
Estimate to complete current year
65.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Upgrade Document Management System
Code
CMW010
Programme
ISG - Communication (COM)
Project Manager
Tim Gray
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
03-Feb-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Category
Compliance