Report for March 2014
- Report Date
- March 2014
Achievements in Last Period
- Preparation completed for DEV upgrade
Issues
- During the first steps of the upgrade a DB issue arose that prevented the CMSDK scripts from completing. Serengeti have identified how this can be fixed but due to availability issues this cannot be scheduled until the week commencing 21/04/14 (to be confirmed).
Next Steps
- Confirmation of revised milestones
- Re do DB prep ahead of DEV upgrade
- Upgrade DEV
Project marked Amber as date not yet confirmed by Serengeti
- Approved budget
- 86.0 days
- Activity this month
- 11.5 days
- Activity this year
- 18.0 days
- Activity to date
- 18.0 days
- Estimate to complete current year
- 65.0 days
- Estimate to complete future years
- 0.0 days