Report for December 2014
- Report Date
- December 2014
Achievements
- Handover competed
- issue with start up scripts resolved
Issues
- System crash in December has prevented deployment sign off. Agreement has been reached with Production that if the system remains stable to mid January the project will move to closure
- A patch expected in December has been pushed out. If this is released before the project closed the project will implement otherwise this will be competed as service work
Next Steps
- Complete deployment review
- Close project
- Approved budget
- 117.0 days
- Activity this month
- 3.0 days
- Activity this year
- 49.0 days
- Activity to date
- 113.5 days
- Estimate to complete current year
- 2.5 days
- Estimate to complete future years
- 0.0 days