Status Report for September 2019

Report Date
September 2019

Summary

Planning continues on preparation for implementation.  Wireless survey review meetings have been completed and information fed into the low level design workshops in October. 

Low level design workshops are in progress and due to complete early October, with central technology staging due to complete in December 2019.  Implementation of central technologies into the live environment is expected to commence early January and complete around mid-late February 2020.  This will be followed by early adopter edge site installations, and a full review of this early implementation will take place late March 2020 prior to commencing full rollout.  Full rollout is currently anticipated to complete around June 2021.

Achievements in Last Period

  • meetings complete for review of wifi survey results
  • discussions on changes to IT practice and service model continue
  • design workshops continue
  • project plan development continues

Issues and Risks

 

Next Steps

  • amendments to the Major Governance Assessment survey toolkit
  • draft detailed implementation plan ready for discussion with Leads
  • meetings arranged with College IT Leads/ACE IT Lead/CSG/USG Lead to continue discussions on high level implementation approach
  • invitations to test Major Governance Assessment survey (will commence after first Programme Board)
  • discussions on changes to IT practice and service model continue
  • design workshops complete

 

Future Milestones

Deliver Migration of campus distribution sites No date available No
Deliver Migration of ACE/ResNet distribution sites No date available No
Deliver Early adopter edge sites No date available No
Deliver Roll out edge/wireless for College of Science and Engineering No date available No
Deliver Roll out edge/wireless for College of Medicine & Veterinary Medicine No date available No
Deliver Roll out edge/wireless for College of Arts, Humanities and Social Sciences No date available No
Deliver Roll out edge/wireless for ACE/ResNet No date available No
Deliver Roll out edge/wireless for Support Services/Others No date available No
Analyse In Room AP Pilot No date available No
Plan Low level design workshops complete 18-Oct-2019 No
Initiate Planning 31-Oct-2019 No
Execute Implementation of Central Technologies 14-Feb-2020 No

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
450.0 days
Activity this month
29.5 days
Activity this year
135.5 days
Activity to date
135.5 days
Estimate to complete current year
251.5 days
Estimate to complete future years
100.0 days

Project Info

Project
Network Infrastructure Deployment
Code
CIS014
Programme
ITI - Communications Infrastructure (CIS)
Management Office
ISG PMO
Project Manager
Rick Arnautovic
Project Sponsor
Anthony Weir
Current Stage
Design
Status
In Progress
Project Classification
Transform
Start Date
07-Jan-2019
Planning Date
31-Oct-2019
Delivery Date
30-Jul-2021
Close Date
27-Aug-2021
Programme Priority
1
Overall Priority
Highest
Category
Compliance

Documentation

Not available.