Status Report for September 2019
- Report Date
- September 2019
Summary
Planning continues on preparation for implementation. Wireless survey review meetings have been completed and information fed into the low level design workshops in October.
Low level design workshops are in progress and due to complete early October, with central technology staging due to complete in December 2019. Implementation of central technologies into the live environment is expected to commence early January and complete around mid-late February 2020. This will be followed by early adopter edge site installations, and a full review of this early implementation will take place late March 2020 prior to commencing full rollout. Full rollout is currently anticipated to complete around June 2021.
Achievements in Last Period
- meetings complete for review of wifi survey results
- discussions on changes to IT practice and service model continue
- design workshops continue
- project plan development continues
Issues and Risks
Next Steps
- amendments to the Major Governance Assessment survey toolkit
- draft detailed implementation plan ready for discussion with Leads
- meetings arranged with College IT Leads/ACE IT Lead/CSG/USG Lead to continue discussions on high level implementation approach
- invitations to test Major Governance Assessment survey (will commence after first Programme Board)
- discussions on changes to IT practice and service model continue
- design workshops complete
Future Milestones
| Deliver | Migration of campus distribution sites | No date available | No |
| Deliver | Migration of ACE/ResNet distribution sites | No date available | No |
| Deliver | Early adopter edge sites | No date available | No |
| Deliver | Roll out edge/wireless for College of Science and Engineering | No date available | No |
| Deliver | Roll out edge/wireless for College of Medicine & Veterinary Medicine | No date available | No |
| Deliver | Roll out edge/wireless for College of Arts, Humanities and Social Sciences | No date available | No |
| Deliver | Roll out edge/wireless for ACE/ResNet | No date available | No |
| Deliver | Roll out edge/wireless for Support Services/Others | No date available | No |
| Analyse | In Room AP Pilot | No date available | No |
| Plan | Low level design workshops complete | 18-Oct-2019 | No |
| Initiate | Planning | 31-Oct-2019 | No |
| Execute | Implementation of Central Technologies | 14-Feb-2020 | No |
- Approved budget
- 450.0 days
- Activity this month
- 29.5 days
- Activity this year
- 135.5 days
- Activity to date
- 135.5 days
- Estimate to complete current year
- 251.5 days
- Estimate to complete future years
- 100.0 days