Status Report for March 2019

Report Date
March 2019

Summary

All progress on the implementation will be reported on this site now as CIS009 winds down towards contract sign off.

Planning has been underway since late 2018, and will continue during the pre-contract award stage with the successful bidder.  Workshops are planned for April/May to fine tune the connectivity, wired and wireless information provided during the procurement process.  This will help prepare for low level design workshops and help the successful bidder fully understand the infrastructure of the network in detail.  Reviews of the wireless surveys will be undertaken (internal staff only) with a range of contacts for buildings which highlighted areas of concern in respect of coverage, or where specific issues have been identified, or use/purpose of the area has changed, and these will also be used to support the low level design workshops after contract award.

Achievements in Last Period

  • information gathering continues to support implementation (e.g.  connectivity, essential services cabinets etc)
  • planning for meetings with Technical Managers/Building Managers etc re wifi survey results continues
  • high level roll out planning continues

Issues and Risks

  • tbc

 

Next Steps

  • planning for implementation continues
  • meetings arranged with Technical Managers/Building Managers and key contacts agreed, re wifi survey results
  • meetings held with College IT Leads/ACE IT Lead to continue discussions on high level implementation approach
  • planning for low level design workshops following indicative award of contract notice
  • invitations to test Major Governance Assessment survey (will commence after contract award)

 

Future Milestones

Stage Milestone Due Date
Initiate Planning 31-May-2019
Plan Low level design workshops complete 28-Jun-2019
Execute Implementation of Central Technologies 13-Dec-2019

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
450.0 days
Activity this month
4.0 days
Activity this year
14.5 days
Activity to date
14.5 days
Estimate to complete current year
69.5 days
Estimate to complete future years
366.0 days

Project Info

Project
Network Infrastructure Deployment
Code
CIS014
Programme
ITI - Communications Infrastructure (CIS)
Management Office
ISG PMO
Project Manager
Rick Arnautovic
Project Sponsor
Anthony Weir
Current Stage
Design
Status
In Progress
Project Classification
Transform
Start Date
07-Jan-2019
Planning Date
31-Oct-2019
Delivery Date
30-Jul-2021
Close Date
27-Aug-2021
Programme Priority
1
Overall Priority
Highest
Category
Compliance

Documentation

Not available.