Status Report for February 2019
- Report Date
- February 2019
Summary
Whilst procurement continues, work has commenced on planning the implementation of the replacement network. This project will overlap with the procurement until contract award is complete, but both project sites will be updated.
Achievements in Last Period
- meetings held with College IT Leads/ACE IT Lead to discuss implementation approach
- information gathering continues to support implementation (e.g. connectivity, essential services cabinets etc)
- planning for meetings with Technical Managers/Building Managers etc re wifi survey results continues
Issues and Risks
- tbc
Next Steps
- planning for implementation continues
- planning for meetings with Technical Managers/Building Managers etc re wifi survey results continues
- invitations to test Major Governance Assessment survey (will commence around May 2019)
Future Milestones
| Stage | Milestone | Due Date |
|---|---|---|
| Initiate | Planning | 31-May-2019 |
| Plan | Low level design workshops complete | 28-Jun-2019 |
| Execute | Implementation of Central Technologies | 13-Dec-2019 |
- Approved budget
- 450.0 days
- Activity this month
- 6.5 days
- Activity this year
- 10.5 days
- Activity to date
- 10.5 days
- Estimate to complete current year
- 73.5 days
- Estimate to complete future years
- 366.0 days