Status Report for February 2019

Report Date
February 2019

Summary

Whilst procurement continues, work has commenced on planning the implementation of the replacement network.  This project will overlap with the procurement until contract award is complete, but both project sites will be updated.

Achievements in Last Period

  • meetings held with College IT Leads/ACE IT Lead to discuss implementation approach
  • information gathering continues to support implementation (e.g.  connectivity, essential services cabinets etc)
  • planning for meetings with Technical Managers/Building Managers etc re wifi survey results continues

Issues and Risks

  • tbc

 

Next Steps

  • planning for implementation continues
  • planning for meetings with Technical Managers/Building Managers etc re wifi survey results continues
  • invitations to test Major Governance Assessment survey (will commence around May 2019)

 

Future Milestones

Stage Milestone Due Date
Initiate Planning 31-May-2019
Plan Low level design workshops complete 28-Jun-2019
Execute Implementation of Central Technologies 13-Dec-2019

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
450.0 days
Activity this month
6.5 days
Activity this year
10.5 days
Activity to date
10.5 days
Estimate to complete current year
73.5 days
Estimate to complete future years
366.0 days

Project Info

Project
Network Infrastructure Deployment
Code
CIS014
Programme
ITI - Communications Infrastructure (CIS)
Management Office
ISG PMO
Project Manager
Rick Arnautovic
Project Sponsor
Anthony Weir
Current Stage
Design
Status
In Progress
Project Classification
Transform
Start Date
07-Jan-2019
Planning Date
31-Oct-2019
Delivery Date
30-Jul-2021
Close Date
27-Aug-2021
Programme Priority
1
Overall Priority
Highest
Category
Compliance

Documentation

Not available.